Live line and power generation ensures worry-free electricity for over 2,500 customers, says State Grid Bortala Power Supply Company
Published: Nov 21, 2024 10:29 PM
Photo: State Grid Bortala Power Supply Company

Photo: State Grid Bortala Power Supply Company



 Recently, State Grid Bortala Power Supply Company successfully completed the expansion and reconstruction project of the 110 kV Mingzhu Substation in a live state by utilizing the "Live Working + Power Generation" operation mode, effectively contributing to the steady improvement of the power supply reliability of the power grid and guaranteeing the normal production and living electricity consumption of customers along the line.

It is known that in order to further enhance the power supply capacity of Wenquan county, the company has newly built the 110 kV Qingyuan Substation and initiated the expansion project of the 110 kV Mingzhu Substation to provide power supply for the Qingyuan Substation. To reduce the impact of maintenance power outages on the production and living of numerous electricity customers and further enhance customers' sense of gain in electricity, the company coordinated and cooperated among multiple professions and departments. 

Based on on-site surveys and technical demonstrations, it clearly defined the work tasks, personnel division, operation risk points, safety measures and other contents. By using two 3,000 kVA medium-voltage generator vehicles to supply power to six 10 kV lines, it achieved seamless switching of loads with "zero perception," satisfying the safe and reliable electricity consumption of more than 2,500 households.

To ensure the smooth progress of the renovation work of this substation, relevant personnel of the company rushed to the site one day in advance to take on-site safety measures. At about 18:00 pm on that day, with a clear sound of closing the switch, both of the two medium-voltage generator vehicles were successfully put into operation and transferred to carry all the loads of the subsequent sections of the lines. At 22:50 pm, the renovation work of the 110 kV Mingzhu Substation was completed, the generator vehicles were disconnected from the power grid and withdrawn from operation, and the lines resumed their original operation modes.

This operation lasted for four hours, achieving zero power outage in the subsequent sections of the lines, zero perception by users, and zero loss of loads, comprehensively improving the power supply reliability.